G

Mounting and Installation

ATTENTION! 
There is no universally uniform standard, which could be applied to a VOC sensor (Volatile Organic Compounds). The monitored air contains a large
number of substances to which the sensor responds, and gas mixtures are adjusted. Therefore this sensor does not act selectively, but rather
reflects the overall air quality. In principle, one also cannot state precisely what is "bad air" or what is "good air" because this is a purely subjective
sensation.
The gas inter-exchange in the sensor element happens by diffusion. Depending on the changes to the concentration and the flow velocity of the air
surrounding the sensor, the reaction of the device to the change of concentration may take place with a delay. It is essential to choose an installation
location for the device in which the air stream flows around the sensor. Otherwise the gas exchange may be considerably delayed or prevented.
Automatic calibration of air quality (default)
The automatic background logic is a self-calibrating mechanism that is suitable
for use in applications in which the air quality regularly drops to fresh air level.
This should typically occur during times in which the rooms are unoccupied.
The sensor reaches its normal accuracy after 24 hours of continuous operation
in an environment that has been subjected to a fresh air supply.
The deviation errors remain minimal if the sensor is exposed to fresh air at least
4 times within 28 days. The ABC logic needs continuous operating cycles of more
than 24 hours to operate correctly.
Manual calibration of air quality
After connecting the device, ensure continuous operation for at least 2 hours
using air defined as "normal" air quality.
Manual calibration can be started by pressing the button position,
irrespective of the DIP 3 -switch.
The calibration procedure is started by pressing the "ZERO" button
(for approx. five seconds). This is signalled via the flashing LED.
Then calibration takes place. During this phase, the LED is continuously active
and a 600 second countdown runs.
Putting in operation
After switching on the device, a self-test and tempering period follows.
This process takes around 30 - 50 minutes, depending on the ambient conditions.
It is imperative to perform manual calibration once this process is completed.
The ABC logic can then be optionally activated.
Switching point setting
A switching point between 10 % and 95 % of the measuring range can be selected
using the SET potentiometer.
A potential-free changeover contact is available as a switch output.
Offset
The VOC measured value can be adjusted subsequently using the offset
potentio meter. The adjusting range is ± 10 % of the measuring range.
®
AERASGARD
KLQ - SD – Duct air quality sensor and measuring transducer, Standard
AERASGARD
®
KLQ - W – Duct air quality sensor and measuring transducer, Premium
Type ⁄ WG02
Measuring Range
VOC
KLQ - SD
K L Q -W
0...100 %
KLQ - W
K L Q -W
0...100 %
Hinweis:
Dieses Gerät darf nicht als sicherheitsrelevante Einrichtung verwendet werden!
Output
VOC
(fixed)
0 - 10 V
(switchable)
0 - 10 V ⁄ 4...20 mA
7
DIP switches
VOC sensitivity
LOW
MEDIUM (default)
HIGH
VOC automatic zero point
deactivated
activated (default)
Output
Voltage 0 -10 V (default)
Current 4...20 mA
DIP switches
VOC sensitivity
LOW
MEDIUM (default)
HIGH
Equipment
changeover contact
Rev. 2018 - V32
KLQ - W
DIP 1
DIP 2
OFF
OFF
O N
OFF
OFF
O N
DIP 3
OFF
O N
DIP 4
OFF
O N
KLQ - SD
DIP 1
DIP 2
OFF
OFF
O N
OFF
O N
OFF
Item No.
IP 43
1501- 3170- 1001-20 0
IP 65
1501- 3150-7301- 200

Publicité

Table des Matières
loading

Ce manuel est également adapté pour:

Aerasgard klq-sd

Table des Matières