Télécharger Imprimer la page

Siemens RVL481 Instructions D'installation page 34

Masquer les pouces Voir aussi pour RVL481:

Publicité

Les langues disponibles
  • FR

Les langues disponibles

  • FRANÇAIS, page 62
en
Wrong
Commissioning
Preparatory checks
1. DO NOT switch on power yet.
2. Check wiring according to the plant connection diagram.
3. Ensure correct position and location of levers by turning the fixing screws. Refer to illustra-
tion on the lateral wall of the controller:
4. Insert unit in the base until stop is reached. Marking TOP must be at the top!
5. Tighten fixing screws alternately.
6. Check controlling element (seat or slipper valve): See if
– it is correctly installed (observe direction of flow indicated on the valve body) 87
– the slipper travels in the correct angular range (note position indicator)
– the hand lever is disengaged
Building Technologies
Place tongues correctly – they
may not be inside the cutout!
Correct
74 319 0618 0 a
17.04.2008
34/276

Publicité

loading