EN │ 8. Electrical connection

8. Electrical connection

DANGER
Danger to life from electric shock.
 Prior to accessing the connection
terminals, switch off all supply circuits.
Switch off mains fuse, secure against
being accidentally switched back on and
position a visible warning sign.
NOTICE
Risk of damage to unit in the event of
short-circuits.
 Insulate any unnecessary cable cores.
Information
● Always note the relevant specifications
for electrical installations and when fitting
equipment. In Germany, observe DIN
VDE 0100 and the corresponding parts
in particular.
● The technology used in the phase angle
controller may cause humming noises.
1. Switch off mains fuse and prevent from
being started up again. Attach warning
sign.
NOTICE
Danger of short-circuits and damage to
the unit. Water may penetrate the ter-
minal box if the connecting ducts are
inserted incorrectly or if the cable
screw-connection is not fitted correctly.
The degree of protection can no longer
be guaranteed.
 Install the cable screw-connections such
that the power cable is held snugly in
place.
2. Fix the suitable cable screw-connections
in the housing and insert allconnecting
cables in the terminal box, so that the
cable screw-connections fit around the
cable sheathing completely.
14
3. Wire unit to the terminal block according to
the wiring diagram ( chapter 14). Note
the screws' tightening torque of 0.7 Nm.
4. Check the position of the jumper [13] in
the EALT 6 terminal box ( chapter 5)
and plug them in again if necessary. Take
EAT 6 G/1 or EAT 6 TG settings into
account.
Temperature limit value switch-off
= On (Ein).
Temperature limit value switch-off
= Off (Aus).
5. Fit terminal box cover [6]. Ensure that the
sealing in the cover is inserted correctly
and is sealed all the way around.
6. Close cover [5]. The cover must audibly
snap into place and be locked.
If necessary, the cover [5] can also
be screwed on.

9. Commissioning

1. Check that connection data matches
technical data on the unit ( rating plate
 unit, instructions envelope).
2. Switch on mains fuse, remove warning
sign.
3. Carry out a function test.

10. Cleaning

In case of the build-up of dust and dirt, clean
the housing with a dry cloth. Cleaning
intervals depend on the build-up of dust and
dirt and cannot be determined in advance.
Do not use any aggressive cleaning agents.

11. Fault rectification

● Call on the services of a trained electrician
any time there is a fault.
● Repairs should only be carried out by a
trained electrician.

Publicité

Table des Matières
loading

Ce manuel est également adapté pour:

Eat 6 g/1Eat 6 tg

Table des Matières