INSTALLATION PROCEDURE

Proceed steps 1 to 7 for each charge point and
continue to step 8.
1. Prepare the cabling (see installation specifications).
2. Attach the wall bracket at the desired height (+/- 1
metre) on the wall.
3. Twist the socket lid or dummy socket counter-clockwise
and out of the cover of the charge point. Then pull the
cover from the rear edge to open the charge point.
Do not use any objects or tools to do this.
4. Put the charge point on the wall bracket to check its
placement. On the wall, mark the positioning of the
bottom two attachment points of the charge point
and select the appropriate fixtures (plugs, screws and
washers).
5. Secure the charge point to the wall bracket using
the two M8 x 12 mm bolts and washers provided.
Then secure the charge point to the wall using the
bottom two attachment points. Ensure that the grey
spacers are placed on the back of the charge point
at the bottom two attachment points.
6. Select the appropriate grommet that suits the cable
width and place it on the opening of the power cable
inlet. Moisten if necessary to make it easier to feed
the power cable through.
7. Secure the power cable using the cable clamp: fasten
the earth wire to the DIN rail-mounted terminal blocks.
8. Phase distribution:
a. Distribute for an optimal use of each phase depen-
ding on parking behaviour (first cars to arrive will not
park next to each other).
b. Fasten the phase and neutral wires to the DIN
rail-mounted terminal blocks.
c. Adjust the phase distribution for every 3 charge
points and note down the phase distribution and
serial number for each charge point (see table 1).
9. Connect UTP cables per charge point:
a. Insert UTP cables using the sockets provided
left and right of the power cable inlet (see figure 2).
Measure 25 cm extra UTP cable from the bottom side
of the charge point.
N.B.: Please contact NewMotion for further (remote) configuration of the Dynamic Load Balancing group.
Please keep the installation details on hand.
N.B.: The charge points must have been activated online to enable charging. Activation can easily be done on my.newmotion.com using the
charge points serial numbers (situated on the right side of the casing). The charge card must also be activated.
INSTALLATION INSTRUCTION – P6
b. If a daisy chain configuration is used, connect the
UTP cables coming from the other charge points to
the left 2 Ethernet ports on the network board (see
figure 2). Both ports can be used in random order.
10. Attach the black grommet to the opening next to the
power cable inlet to make the charge point watertight.
11. Note when using a pole: Earth the pole with the earth
wire via the lower right bolt attachment on the charge
point (see figure 2).
12. Connect the power cable to the mains in regular order
(no adjustments: L1L2L3).
13. Switch the charge point power on. A yellow LED
shines for about 30 seconds before the charge point
starts up.
14. Check if all UTP cables are properly connected.
If the communication between the charge points is
successful, the LED indicators of the Ethernet ports
should be blinking green.
15. Make sure that the charge point which will be appoin-
ted as unit to control the load balancing group has
sufficient GPRS signal strength and can connect to
the NewMotion back-office. A quick check can be
done on chargeportal.newmotion.com/test. Simply
enter the serial number into the search field and click
'Search'. 'Online' should appear after the serial num
ber. If 'Online' does not appear, check whether the
charge point is properly connected and try again. For
persistent issues, please contact NewMotion.
16. Place the cover on the charge point. Tighten the four
M4 x 12 mm bolts provided around the socket so that
the cover closes on the rubber seal but the rubber
seal does not deform. Tighten the other two M4 x 12
mm bolts provided on the bottom of the cover.
17. Twist the socket lid or dummy socket clockwise in the
cover and lock using the M4 x 20 mm bolt provided.
The bolt must be secure, but not too tight.
18. Apply the appropriate stickers provided onto the
designated indented spaces of the charge point's
sides.
19. In the distribution board, indicate which MCB(s) are
connected to the charge points.