INSTALLATION SPECIFICATIONS
3-phase
11 - 22 kW
RCD 3-phase
Power cable above
ground
Power cable
underground
Cable attachment
Dynamic Load Balancing
One power cable
* Always wire for the maximum hardware amperage under continuous load. Cable diameters are an indication,
NewMotion advises to always use one size larger. The electrician is responsible for selecting a cable thickness appro-
priate for your specific situation.
** The electrician must select an MCB to match the maximum amperage setting of the charge point.
INSTALLATION INSTRUCTION – P2
Wiring*
< 50 m
50 – 100 m
5 x 6 mm
5 x 10 mm
2
2
30 mA Type B (maximum four circuits behind one RCD)
XLPE Insulated unarmoured PVC Sheathed
XLPE Insulated Armoured PVC Sheathed
PVC tube with clamping brackets and saddles
Standard CAT5 or CAT6 UTP cable with RJ45 connector
Each charge point has terminal blocks to split the power feed. A group of charge
points can share up to 3-phase 32A in total. Depending on the charging behaviour or
requirements, a maximum of 6 charge points can be connected to one power feed.
The wiring between the charge points should have the appropriate thickness for the
specific situation, calculated with the maximum distance between the distribution
board and the charge points.
Setting
MCB**
16 A
20 A B-Curve
20 A
25 A B-Curve
32 A
40 A B-Curve