Installation; Installation Of The Neo Pro Charger; Check The Power Supply Cut; Check The Connections - Ingeteam NEO Pro Manuel D'installation Et Usage

Table des Matières

Publicité

Les langues disponibles

Les langues disponibles

Ingeteam

3. Installation

3.1. Installation of the NEO Pro charger

3.1.1. Check the power supply cut

Make sure the power supply is interrupted at the point of installation of the charger.

3.1.2. Check the connections

Check that the required electrical wiring for powering the charger is available at the point of installation.
OPTIONAL: If a CURVE device will also be installed, check that the wiring from that device is also available. For
more information, see
"Installation of the CURVE
OPTIONAL: If the charger will be connected to a three-phase energy meter, communications equipment (modem,
router, switch, etc.) or another charger, check that the Ethernet wiring from that device is also available. For
more information, see
"Installation of the CURVEx3"
communications
element".

3.1.3. Optional: install the stand element

If it is necessary to install the STAND element to anchor the charger to the ground, see
element
(optional)".

3.1.4. Place the template

Place the template in the desired position, approximately 1.2 m from the horizontal reference to the ground.
CAUTION
It is recommended to use a level to ensure that the template is perfectly level.
10
device".
and/or
"Connection of the charger to another charger or a
ABV2012IQM01_ - Installation and Operation Manual
Installation
"Installation of the STAND

Publicité

Table des Matières
loading

Table des Matières