PR0-PAC SYSTEM OWNER INSTALLATION MANUAL
INSTALLATION
1. SITING
1.
Ensure heat pump on site is as ordered, i.e. model, electrical supply
and factory fitted options.
2.
Inspect unit for damage, in particular inspect the evaporator
(finned side) to ensure that it is undamaged. (Minor indentations in
the fins do not affect performance). If severely damaged, endorse
delivery note in presence of the driver and send a recorded
delivery letter to transport company giving details.
3.
Protect unit if installation is delayed.
4.
Provide a firm level base capable of supporting operational weight
of unit; spread load on timber floor.
5.
Ensure water cannot collect under unit - recommend units are
installed on plinths 100mm above finished floor level and to also
aid condensate drainage.
6.
Allow adequate clearance to service panels on unit; recommend
500mm minimum (see installation drawings).
IMPORTANT NOTE
6
7.
All Calorex heat pumps are by design as quiet as is practical,
however due consideration should be given to siting in order to
fully exploit this feature, i.e. ensure that the inlet and outlet grilles
face away from occupied property.
8.
Ensure loose debris such as leaves, grass cuttings, etc will not
block air inlet grilles.
9.
Consider protection from extreme weather conditions if installed
externally, i.e. lean-to-cover or building.
Lift the unit into place using a fork lift truck, or similar lifting
device, if lifting the unit from above spreader bars must be
used to avoid any pressure on the sides of the unit or packing
materials.
DO NOT PUSH OR DRAG THE UNIT ALONG THE GROUND.