INSTALLATION:
The installation site is crucial; make sure that nothing interferes with the smooth operation of the T-LINE system when it is installed (overhead crane,
electrical cable, safety cable, passage of machinery, etc.).
1
The device
and its redirection pulley
of 19 kN. Anchorage systems must be suitable for the host structure.
If the installation concerns a T-LINE System with rescue hoist, take into consideration that the lifting rescue operation will always bring the victim back
to the main T-LINE device (in other words, to the operator operating the rescue handle). It is therefore essential to have constant access and a suitable
and secure workstation on this side for a rescue operation in good conditions.
1
The device
and its redirection pulley
structures such as concrete, metal structures, etc.
Installation of specific anchorages FA 60 039 01: This is the preferred installation when allowed by the host structure.
The specific anchorages must be fixed by means of 4 fasteners (screws, plugs) adapted to the support in which they will be
installed.
Using the nature of the receiving structure and the site's configuration, an engineer must run calculations to determine that the
sizing of fasteners, the type of fixture (chemical or mechanical fasteners, etc.), the position of the fasteners, and thus of the
mounting bracket, are all correct.
Tightening torque:
Nut and screw tightening torque:
M12: 110 Nm
Installation with anchorage straps/slings:
WARNING! The installation of the system with webbing and cable slings is prohibited!
The fall arrest system can be severely impacted using webbing and cable slings due to the large freedom of movement of the T-LINE SYSTEM and its
pulley.
Installation on other types of anchorages:
Make sure they are strong: R > 19 kN. They must not allow the device
2
The redirection pulley
must be positioned via its anchorage eye
2
redirection pulley
can be installed higher, taking care that the angle of the section of the secondary cable
2
pulley
is no more than 15° from horizontal.
It must be installed such that the user cannot end up above the T-LINE's secondary cable
increase considerably, as would the impact on the user and the transfer of forces to the structure.
Photo 1
2
must be attached to anchorage systems that comply with standard EN 795 AND/OR with a minimum strength
2
can be fixed on specific anchorages (reference FA 60 039 01) (Photo 1- Photo 2); these can be adapted to
Chemical anchor tightening torque:
M12: 40 Nm
1
4
Photo 2
Mechanical anchor tightening torque:
M12: 60 Nm
or its redirection pulley to move
at the same level as the anchorage eye
6
, in which case, when falling, the stopping distance would
13
2
.
3
1
of the device
; alternatively, the
6
1
between the device
and its redirection