3. Installation and Wiring
8. Connect the battery jumper cables on both sides of the UPS (Figure 3-13).
• Right side of the UPS: connect the batteries with 36 battery jumper cables
• Left side of the UPS: connect the batteries with 18 battery jumper cables
9. Connect the three battery packs to the positive fuse (Figure 3-14).
Notes:
• For steps 9 through 12, the torque for the M6 screw is 5 N•m for the fuses and bus bar.
• For Steps 9 through 12, the cable numbers reference the wiring diagram in section 3.10 for installation of 60 batteries.
Battery
Jumpers
Figure 3-13: Connect Battery Jumper Cables
Figure 3-14: Connect Battery Packs to Positive Fuse