Start-Up - Homa FV 50 Manuel D'instructions Original

Table des Matières

Publicité

Les langues disponibles

Les langues disponibles

At the cleaning opening (from DN200)
First, loosen the screws (5) on the pump housing (1) and remove the cover of the cleaning opening. Then, attach the new
cleaning opening cover (3) to the pump housing (1) using the screws (4). Then screw in the flush valve (2) with the medi-
um-strength screw lock and arrange it vertically.

5.2. Start-Up

For the commissioning, please also read the operating manual from the respective pump being used.
The initial commissioning, it is recommended to clean the pump pit in advance. It is possible that old deposits may be agita-
ted and the can be placed in the flush valve.
The outlet jets always have to be installed on the flush valve.
In order to reach the recommended flush time of approximately 30 seconds, the flush valve can be set on the current
restrictor. For the commissioning, we recommend that the current restrictor be set to '1' and the effective flush time
during operation be noted. If you would like to reach a longer flush time thereafter, the current restrictor must be set to
a higher level.