Notes on programmer - Programmer sequence
Time key
time (50 Hz)
in seconds
31,5
t1
Pre-ventilation time with open air gate
3
t2
Safety time
-
t2'
Safety time or first safety time with burners using pilot burners
6
t3
Short pre-ignition time (ignition transformer on terminal 16)
-
t3'
Long pre-ignition time (ignition transformer on terminal 15)
12
t4
Time between the t2' start and the consensus to the valve on terminal 19 with t2
-
t4'
Time between the t2' start and the consensus to the valve on terminal 19
12
t5
Time between t4 end and the consensus to the power regulator or the valve on terminal 20
18
t6
Post-ventilation time (with M2)
3
t7
Time between consensus upon start-up and the voltage to terminal 7 (start delay for fan motor M2)
72
t8
Start-up duration (without t11 and t12)
3
t9
Second safety time for burners using pilot burners
12
t10
Time from start-up to the beginning of the air pressure control without air damper real travel time
t11
Damper opening travel time
t12
Damper travel time in low flame position (MIN)
18
t13
Allowed post-combustion time
6
t16
Starting delay of consensus to air damper OPENING
27
t20
Time up to automatic closure of the programmer mechanism after burner start-up
NOTE: With voltage at 60 Hz the times are reduced by nearly 20%.
30 / 44
0006080103_201309
Output signals on terminal board

Publicité

Table des Matières
loading

Ce manuel est également adapté pour:

Gi mist 420 dspgmGi mist 510 dspgm

Table des Matières