Start up the inverter.
① Set the DC Switch-Disconnector to the ON position.
② Confirm that the cabinet LCD panel looks similar to the screen shown below.
* The remote control panel should read "VERIFY STAND-ALONE
OPERATION AND COMMUNICATION WITH THE STORAGE
BATTERY UNIT." Values are approximated.
Bus Voltage: Approx. 420
Operating Mode
(Default setting: BACmod)
4
Confirm communication between the storage battery unit and stand-alone operation.
① Check the remote control panel display.
"MANUAL GRID STOP" should be displayed.
② Press the [RUN/STOP] button on the remote control panel.
The button will turn red.
The amount of solar power generated and the storage battery
charge amount will be displayed.
The maximum amount of power charged to the storage
batteries is 1.5 kW. (0 to 1.5 kW will be shown depending on
the amount of sunlight). Since no loads (electric appliances) are
connected to the inverter, 0.0 to 0.3 kW is shown as the
difference between the solar power generated and stored
power. This is the amount of output power is required to
maintain the operation of the inverter.
When solar power is not being generated, power is discharged
from the storage batteries. On the storage battery unit, the
status indicator light for the MODE will be green when charging
and orange when discharging.
5
Check the power supply to the stand-alone input terminals (U1, V1).
Confirm that the voltage at the stand-alone
input terminals is 120 ± 5 V.
Test Points
Storage battery charge (%)
Not for customer use