Nefi18H Log Placement - Napoleon Woodland NEFI18H Manuel D'installation

Masquer les pouces Voir aussi pour Woodland NEFI18H:
Table des Matières

Publicité

Les langues disponibles

Les langues disponibles

WARNING
!
Power supply service must be completed prior to fi nishing to avoid reconstruction.
Heat vents and air openings cannot be covered in any circumstances.
4.1

NEFI18H log placement

1
Place the log (#1) onto the pins. Ensure the log is
secure onto the pins, as shown.
3
#3
Place the log (#3) into the groove. Ensure the log is
secure, as shown.
PIN
#1
2
#2
Place the log (#2) onto the pins. Ensure the log is
secure onto the pins, as shown.
4
Place log (#4) into the groove. Ensure the log is
secure, as shown.
4.0 fi nishing
fi nishing
PIN
#4
13
W415-1654 / D / 02.18.20
EN

Publicité

Chapitres

Table des Matières
loading

Table des Matières