Indoor unit

Fixing Installation Plate

The wall you select should be strong and solid
enough to prevent vibration.
1
Before installation, confirm the position of a
screw between chassis and Installation
plate.
2
Mount the installation plate on the wall with
type "A" screws. If mounting the unit on a
concrete wall, use anchor bolts.
- Mount the installation plate horizontally by
aligning the centerline using Horizontal
meter .
Installation Plate
Chassis
Hook
3
Measure the wall and mark the centerline.
It is also important to use caution concern-
ing the location of the installation plate.
Routing of the wiring to power outlets is
through the walls typically. Drilling the hole
through the wall for piping connections
must be done safely.
A-Type
B-Type
Type "A" Screws
16.22(412mm)
Unit
Outline
Ø65
Place a level on raised tab
Installation Plate
5.35
(136mm)
7(178mm)

Drill a Hole in the Wall

- Drill the piping hole with a ø65mm hole core
drill. Drill the piping hole at either the right or
the left with the hole slightly slanted to the
outdoor side.
WALL
Indoor

Flaring Work

Main cause for gas leakage is due to defect of
flaring work. Carry out correct flaring work in
the following procedure.
Cut the pipes and the cable
1
Use the piping kit accessory or the pipes
purchased locally.
2
Measure the distance between the indoor
and the outdoor unit.
3
Cut the pipes a little longer than measured
distance.
4
Cut the cable 1.5m longer than the pipe
length.
Copper
90°
pipe
18.90(480mm)
Ø65
4.84
(123mm)
(Unit : in)
9.65(245mm)
Outdoor
Slanted Uneven Rough