5. INSTALLATION PROCEDURE
The powercable connection on the terminal block of
the chargepoint should match the L1, L2 and L3 in the
chargepoint. For a 1 phase installed chargepoint the L1
measurement head should match the conduction which
is connected to the L1 of the terminal block.
Warning: Keep module switched off during installation
Step 1: Feed the UTP cable(s) through the rubber stop(s)
on the data cable inlet;
Step 2: Clamp a RJ12 connector straight to the cable
and then connect it to the P1 port, as indicated in the
'3.4.2 Overview Installing Accessories' section;
Step 3: Don't plug the power adapter in the power outlet
yet;
Step 4: Connect the power adapter to the Load
Shedding module. One of the two power adapter wires
has a broken white stripe. This wire is the power adapter
GND and should therefore be connected to the GND pin
(right) on the module. The other wire is the +5 Volts and
should be connected to the +5V pin (left) on the module.
The middle pin is not used;
Step 5: Connect the CT('s) to the Load Shedding
module;
Step 6: Install the Load Shedding module on the DIN
Rail in the fuse box;
Step 7: Apply the CT('s) to the grid connection(s). Make
sure to apply the CT(s) so that the total power usage of a
phase is measured;
Step 8: Plug the power adapter into a power outlet. The
PWR LED must light up;
Step 9: The CS LED will (after a few seconds) indicate a
measured current after the power is on;
Step 10: Prepare the cable between chargepoint and
Load Shedding module. The maximum length of the
cable between charge point and Load Shedding module
is 20 meters.
Step 11: Plug in the RJ12 cable to the Load Shedding
module
If both ends of the cable are properly connected to
the charge point & Load Shedding module and powered,
the P1 LED will indicate whether the connection is
correct.
INSTALLATIEHANDLEIDING – P27
INSTRUCTION MANUAL – P27 | P27
5.6 LOCAL CONFIGURATION (UTP)
Make sure both the charge point and laptop are
powered on for at least 5 minutes.
Continue to Chapter 6 and follow instructions for local
configuration.
5.7 FINISHING UP (CLOSE ENCLOSURE)
Step 1: Check and make sure that the rubber seal
around the casing is properly in place on the edge;
Step 2: Place the cover on the charge point;
Step 3: Hand-tighten the four M4 x 12 mm bolts
provided around the socket so that the cover closes on
the rubber seal but the rubber seal does not deform;
Step 4: Hand-tighten the other two M4 x 12 mm bolts
provided in the bottom of the cover;
Step 5: Turn the socket lid clockwise in the cover and
hand-tighten the M4 x 16 mm bolt provided;
Step 6: Switch on power to the charge point;
Step 7: Wait until charge point is fully started up (+/-10
minutes, LED should be off)
VERSION 0129NM02INT01
0520NM19INT03

Publicité

Table des Matières
loading

Ce manuel est également adapté pour:

Renault edition home basic 11 kw

Table des Matières