WORKING FIELD
E
N
G
L
I
S
H
The working fields are obtained from test boilers corresponding to the standard EN676 and are indicatively for the combination burner-
boiler. For correct working of the burner the size of the combustion chamber must correspond to current regulations; if not the manufac-
turers must be consulted.
POWER SUPPLY LINE
The gas supply scheme is shown in the diagram below. The gas train is certified in accordance with regulations EN 676 and is supplied
separately from the burner. A manual shut off valve and anti-vibration joint must be installed upstream of the gas valve, as shown in the
diagram.
GENERAL GAS BURNER SYSTEM
Legend
1) Manual shut off valve
2) Anti-vibration joint
3) Gas filter
4) Minimum gas pressure switch
5) Safety valve
6) Pressure regulator
7) Valves seal control device
8) Working valve
TBG 45ME
Gas train
supplied by the manufacturer
9) Air adjustment servo motor
10) Air adjustment gate
11) Air pressure switch
12) Combustion head
13) Gas adjustment throttle
14) Gas adjustment servo motor
6 / 15
0006081370_200807
TBG 60ME
The job of the installer