Installation
­ Burner assembly
420010355104
5
4
3
Burner pipe insertion depth and
brickwork
Unless otherwise specified by the boiler
manufacturer, heat generators without a
cooled front wall require brickwork or
insulation 5 as shown in the illustration.
The brickwork must not protrude beyond
the leading edge of the flame tube, and
should have a maximum conical angle of
60°. Gap 6 must be filled with an elastic,
non-combustible insulation material. For
boilers with reverse firing, the minimum
burner tube insertion depth A as
specified in the boiler manufacturer's
instructions must be observed.
On boilers the blast tube insertion depth
should be observed as per the boiler
manufacturer's instructions.
Reverse flame boiler :
A = 50-100 mm.
Three pass boilers :
A1 = 50-100 mm.
Burner assembly
The burner is fixed by mean of connecting
flange and therefore to the boiler.
Installation:
• To fix the flange 3 to the boiler with
the screws 4.
• Turn the burner slightly, guide it into
the flange and secure using screw 5.
Removal:
• Loosen screw 5.
• Turn the burner out and pull it out of
the flange.
Oil connection
The filter must be located in such a way
that the correct hose routing cannot be
impaired. The hoses must not kink.
A
A1
Exhaust system
To avoid unfavourable noise emissions,
right-angled connectors should not be
used on the flue gas side of the boiler.
www.ecoflam­burners.com
EN
11