2.3.
Venting
Inlet and outlet lines on grease separators must be adequately vented.
The inlet line must be run as a ventilation duct up to the top of the roof.
All connecting lines longer than 5m must be vented separately.
If no ventilation is provided for the inlet line over a distance of ten metres, another
ventilation duct must also be connected as close to the separator as possible.
A draught intensifier supports the ventilation.
2.4.
Building site
The tank must only be installed in non-cohesive soil to slightly cohesive soil (G1 group,
condition A4 and B4, degree of compaction DPR = 97 %, according to ATV-DVWK-A
127). In case of deviating installation conditions, a separate verification must be carried
out.
Vor der Installation müssen folgende Punkte unbedingt abgeklärt werden:
The structural suitability of the ground.
Maximum occurring ground water levels and infiltration capacity of the ground.
To determine the soil physical factors, a ground assessment must be carried out.
2.4.1. Ground level cover
Attention: The ground level cover over the tank collar must be between 700 and 1200 mm!
Saphir tank series
700 - 1200
2. Installation conditions
KLsepa.pop
Diamant tank series
700 - 1200