articles C48 in a permanent manner. Position article D34 to cover the plates with elements B12 and C62 and
drill with a Ø 8 mm point. (fig.4) (fig.5).
9. Insert the intermediate support N21 into the final support N20. Secure at the bottom using a self-locking
wrench before tightening. Assemble the tread with screws C53; propping the support as you continue to
assemble the structure and the treads so that its weight is not borne by the floor. A prop must be inserted
every 4/5 supports. For safety reasons, climbing on the staircase before it is fastened to the floor (point 13)
and stiffened (point 14) is strictly prohibited. Position the rise calculated previously (see point 2) and check
horizontality and alignment with the previous tread.
Warning: check the depth of the going for tread L25, using a through baluster (C03) for articles C71 and ensure
that it is perfectly vertical.
Secure articles B99 in a permanent manner working on both sides of the support to avoid changing the position
(horizontality and verticality) of the tread. Continue, assembling the remaining intermediate supports N21 in the
same manner. For corner treads, drill connecting holes to the support (N20, N21, N22, N23) according to the
direction of rotation chosen. Drill the treads (L25, L26, L27, L28) with an Ø 8.5 mm point at a depth of 30 mm
(fig. 8).
10. Secure article C71 to the inner part of the corner treads L26, L27, and L28 with articles C57 (drill with a
Ø 4.5 mm point at a depth of 30 mm) using a vertical baluster C03 as a reference point. (fig.9)
Warning: secure article C72 on the first tread on the floor near the 1st baluster C81 (fig. 1).
11. Screw article N25 onto support N22 and insert into support N23 (after inserting article N24). Insert article N24
into support N21; then insert support N22. Assemble the treads using screws C53. Position the rise calculated
previously (see point 2). Check its horizontality and alignment with the previous tread and tighten articles B99 in
a permanent manner.
12. Check the verticality of the entire staircase and - if necessary - correct by moving support N23.
13. Dismantle the first tread and mark the holes on the floor. Drill the floor with a Ø 14 mm point, near the holes
present on support N23. Insert the dowels C47 and secure in a permanent manner (fig. 1).
14. Stiffen the staircase in the following points: a) insert column G08 in an intermediate position into the ground
with articles D31, C35 and B20. b) Secure the staircase to the wall using element F12, article B13 (drill with
a Ø 14 mm point) and screws C57 (drill with a Ø 4.5 mm point), only in the points indicated. Cover with article
B95 (fig. 11).
Assembling the railing
15. Assemble elements C63, C65, C66 to the balusters C03 and articles D43, C54, C79 to the 1st baluster C81
(the one with the largest diameter) (fig. 1) (fig. 6).
16. Insert the connecting balusters C03 between the treads. Position the balusters with element C63 so that the
part with the hole points towards the top (fig. 6). Tighten elements B02 onto article C71 (fig. 7).
17. Measure the distance between the three corner treads and cut a baluster C03 to measure. Then connect the
three corner treads using this segment of the baluster. Assemble element C71 with articles C57 to tread L25 at
a distance which allows for article F08 to be assembled between two balusters (fig. 9). Cut the baluster C03 to
measure and assemble in element C71 using articles C57 and B02.
18. Fasten element F34 to the floor near the first baluster (C81) and drill using a Ø 8 mm point. Use elements C58,
B12, B02 (fig.1). Warning: the first baluster must be cut based on the height of the other balusters.
19. Cut the handrail A14 segment to measure (fig. 10) and assemble in succession with article B33 and glue
X01(fig. 1). Secure the handrail to the balusters using articles C64 while maintaining the balusters vertical. Saw
off the excess handrail next to the first (C81) baluster of the staircase using a hacksaw. Complete the handrail
(A14) by securing element A12 using elements C64 and the glue (X01) (fig. 1) (fig. 10).
20. Position elements C71 halfway between the two balusters C03. Cut the intermediate balusters C03 at a height
measurable on the staircase itself. Insert the balusters into elements C71 and position articles C63 towards
the top (fig. 6). Tighten elements B02 (fig. 7). Secure the balusters to the handrail using the screws C64 (fig. 1).
Secure the elements F08 with articles C49 and C50. (Fig.10).
21. To stiffen the railing, fasten the baluster to the wall with article F09 using articles F08.
Drill with a Ø 8 mm point and use elements C49, C50, C58, B12 (fig. 10).
22. Complete railing assembly by inserting elements B82 into the lower part of the balusters (C03) (fig.10).
23. Apply the lower closing articles D27, D28 and D29 (fig. 1).
24. Apply the lateral closing articles D30 as follows:
1) hook the back part to the pre-curved sheet.
2) bring it into contact with the sheet until both elastic hooks in the square holes are released.
After you have finished assembling the staircase,
please visit our website and send us your suggestions: www.pixima.it