Assembly And Installation [Specialist]; Option 1: Installation Onto A Boiler Connection - PAW DN 25 Notice De Montage Et D'utilisation

Collecteur modulaire
Table des Matières

Publicité

Les langues disponibles
  • FR

Les langues disponibles

3 Assembly and installation [specialist]

3 Assembly and installation [specialist]
The modular distribution manifold can be installed such that the connections for the heating
circuits are either directed to the top or to the bottom.
NOTICE
Damage to property!
The location of installation must be dry, load-carrying, frost-proof and protected against
ultraviolet radiation to prevent material damage to the installation.
NOTICE
Damage to property!
The covers at both ends of the distribution manifold must not be turned by 90°.
In this case the flow and the return chamber would be connected, resulting in
undesired circulation.
Keep in mind that the flow is connected to the pipe connection marked "V" and the return is
connected to the pipe connection marked "R".
The distribution manifold can be either mounted onto a boiler connection DN 25 or directly
to the wall with wall brackets. The boiler connection and the wall brackets are not included
in delivery.
3.1

Option 1: Installation onto a boiler connection

1. Choose the position for installation.
2. Connect the boiler connection to the boiler as described in the instructions.
3. Take the distribution manifold out of the insulation.
4. Put the distribution manifold with the sealings onto the boiler connection.
5. The boiler connection is normally equipped with compensation threads.
Use the compensation threads to adjust the distribution manifold horizontally.
6. Firmly tighten the compensation threads.
2017/01
993x1x3-mub-ml – V01
17

Publicité

Table des Matières
loading

Table des Matières