Start-Up; Equipment Inspection; Inspection; Hermetic Sealing Of The Unit - Ingeteam INGECON SUN 1Play TL M Série Manuel D'installation

Masquer les pouces Voir aussi pour INGECON SUN 1Play TL M Série:
Table des Matières

Publicité

Les langues disponibles
  • FR

Les langues disponibles

  • FRANÇAIS, page 133

Start-up

11. Start-up
This chapter details the process for the starting up the unit.

11.1. Equipment inspection

You must check the correct condition of the installation before start-up.
Each installation is different, depending on its characteristics, the country in which it is located or other special
conditions which may apply. In all cases, before starting up, it is necessary to ensure that the installation complies
with the applicable legislation and regulations and that at least the part to be started up is complete.

11.1.1. Inspection

Before inverter start-up, you must carry out a general inspection of the units involving mainly:
Wiring inspection
Check that the cables are correctly joined to their connectors.
Check that these cables are in a good condition and that there are no hazards in their environment which
damage them, such as sources of intense heat, objects which could cut them or arrangements which put
them at risk of impacts or pulling.
Check the polarities of the DC and AC cables.
Check that the unit is properly secured
Check that the unit is secured firmly and is not at risk of falling.

11.1.2. Hermetic sealing of the unit

Ensure during installation operations that the unit's level of sealing has not been altered during connection of the
unit.
Check the correct adjustment of the connectors and that any cable grommets are well sealed.
Check that a torque of 6 Nm has been applied to the housing closure screws.

11.2. Power-up

Once a general visual inspection, wiring check and sealing check have been carried out, connect power to the unit
(DC and AC).
In the first inverter connection a number of screens appear in which you must select, in this order, language,
country and applicable standards. After its configuration a feedback screen appears with the options selected.
After this first configuration, select Main menu > Start/Stop > Start, thus starting the inverter.
ABE2011IQM01_B - Installation and Operation Manual
Ingeteam
DE
EN
ES
FR
IT
PT
75

Publicité

Table des Matières
loading

Table des Matières