Before starting the assembly, make sure that you have all the necessary parts by taking an inventory from the parts list provided on
page 9.
• Installation on concrete slab is mandatory and imperative for warranty validation. Thickness: 20 cm minimum. Make sure that the
slab is perfectly flat, smooth and level.
SUMMARY:

- Wall assembly

1
- Installation of reinforcements and brackets
2
3
- Preparation of the walls
- Installation of bottom felt and liner
4
5
- Cutting out the jetstream installation
- Cutting out the discharge nozzles, brush and skimmer plugs
6
7
- Cutting and installing the spotlight
- Installing the coping stones and anodised aluminium finish
8
9
- Ladders
10
- Connecting the jetstream system
11
- Connecting the filter system
12
- Connecting the heat pump
13
- Connecting the automatic pool floor vacuum cleaner (The pool vacuum cleaner is optional. It is not included in the equipment provided.)
14
- Electrical cabinet
15
- Using the jetstream installation
Wall assembly
• Align the pool so as to position the entrance of the skimmer(s) facing the prevailing winds in order to optimise the evacuation of surface
particles.
1a - Place the wooden posts in the metal bases. There are short (PS1) and long (PS2) metal bases, make sure they are in the right positions!
1b - Retrofit the first row of beams. The tabs are intended to correctly align the beams when they are interlocked; their absence or small breaks do not in any
way affect the mechanical resistance of the wood, the solidity and the assembly of the pool.
1c - Secure these beams in place using the metal studs (corner and right). Fasten with the bottom bolt 12x160 loosely. Position the assembly of the bolts of the J
and K bag: 12 x 160 for the metal bases and 12 x 120 in the upper part of the posts.
1d - Continue assembling the beams using the martyr piece provided for this purpose.
1e - 1f - Place the jetstream beams on rows 6/7/8 in front of the skimmer.
Place the lower and upper skimmer beams on the 9/10 rows in front of the jetstream.
Place the pool spotlight beam in the 6th row on a wall to the left or right of the skimmer.
Place the beam in the 8th row on a wall to the left or right of the skimmer.
1g - Put the remaining beams in place.
1h - Check the alignment of the lower and upper skimmer beams as well as those of the jetstream.
1i - Check the alignment of the shoes (chalk line) and diagonals (10 m tape); A = B
1j - Tighten all bolts on all posts.
1k - Prepare the drilling of the upper beams, respecting the dimensions.
1l - Drill the central hole (diam. 8 mm), strike the first anchor pin 8 x 90 and tighten. Drill the remaining holes (diam. 20 mm), strike the 20 x 160 anchor bolts
and tighten. Repeat the operation on each base.
1m - Nail the finishing boards to the posts. Do the same for RC-1 and RC-2 wood flooring.
Installing reinforcements and brackets
2a - Start by fixing the supplied PRG metal plate below the support boards with the screws. Position the horizontal reinforcements flush with the top edge
to the outside of the structure. Level and screw in from inside the pool until the screw heads are drowned.
2b - Pre-drill 3 holes diameter 6 mm (on the corners).
2c - Enlarge the holes to a depth of 45 mm using a 12 mm diameter flat drill bit and screw in using 3 6x90 screws.
2d - Pre-drill 3 holes of diameter 6 mm and screw to the junctions using 3 screws 6x90.
2e - Position the brackets in the up-down direction, draw their positions, drill and screw until the screw heads are drowned.
2f - Screw the horizontal reinforcement with the brackets.es.
Preparation of the walls
3a - Screw the skimmer vent into the upper beam using 2 round head screws to be removed from the screw bag provided in the skimmer box.
3b - Install the skimmer square outer seal and the skimmer body.
3c - Secure the assembly with the 8 round head screws to be removed from the screw bag provided in the skimmer box, tightening effectively for a good
waterproofing. (Screw in by hand).
3d - Seals. Place a rectangular joint on the skimmer frame, making sure it adheres well. At the outlet and the brush socket, install the cork seal (A) in contact with the
wall and then superimpose one of the 2 white round joints (B), making sure that they adhere well.
3e - Screw the jetstream installation fixing plate fully onto the milled frame using the 24 4 x 35 mm stainless steel screws provided.
3f - Drill the rails to size (3 cm from the ends and then every 20 cm approximately). The rail of a wall can be composed of several segments placed end to end.
3g - Unroll the wall felt.
Before the next step, carefully clean the concrete slab and remove shards or splinters from the walls with abrasive paper to make all supports
clean and smooth.
3h - Attach the plastic rail to the felt underlay of the top plank.
3i - Screw on the first liner rail using the 4x40 stainless steel screws.
3j - At the corners, partially cut into the rail in a "V" shape, so that the profile can be folded. Screw at 3 cm from the corner on both sides, then screw on all the rails.
3k - Cut the felt on the outside of the frame.
3l - Do the same with the return flow, vacuum point and counter-current swimming system frame.
3m - Install the counter-current swimming system body on the mounting plate using the 5x20 stainless steel screws, washers and nuts supplied.
Note: The counter-current system housing must be installed such that the outlet of Ø 75 mm is positioned higher and the suction of Ø 90 mm is positioned lower.
10C page 52.
All the instructions in the present operating manual that refer
to electrical installations (electrical box, counter-current system,
filtration system, swimming pool spotlight and heat pump) must
be performed only by a qualified electrician.