S&P HIT 1.250 Notice D'installation Et D'utilisation Succincte page 19

Table des Matières

Publicité

Les langues disponibles

Les langues disponibles

 Open the protection meshes from the air input side, loosening the screws in the
fasteners on the mesh (Figure 6). Pass the motor piped cable through the
rubber cable grommet previously inserted.
 Ensure that the motor cable has been completely extracted and that it has no
defects and/or cuts.
 Replace the protection meshes and, after having placed the anchoring devices
in the horizontal position, tighten the screws until the device is locked.
5
INSTALLATION
WARNING: The extractor installation and maintenance procedures must only
be performed by adequately trained personnel.
WARNING: The lifting of the machine required to install it in an elevated
position must be carried out under strict safety conditions. Therefore, these
operations must be performed by expert personnel.
 Given the weight, the extractor should be lifted by self-propelled aerial platforms
or forklifts with sufficient lifting capacity.
 The performance characteristics of the lifting devices employed should be well
above the performance required to lift the extractor.
 If using lifting straps, they should have a capacity of at least three times the
weight of the extractor.
 The use of the personal protection equipment (PPE) is required as indicated in
section 2.1 of this manual.
NOTE: Under no circumstances will S&P be liable for the damages to things
and/or persons due to incorrect procedures regarding the movement of the
machine or the use of inappropriate equipment.
 Check and make sure that, on the air intake side, the area is free from all
obstacles and/or buildings for a distance of at least 10 metres.
 In the wall, there should be a square hole 10mm larger than the size of the
device to facilitate insertion (Figure 7).
NOTE: Figure 8 shows the general dimensions / weight of the range of S&P
HIT / HIB fans. The net weight of each model is also indicated on the
characteristics plate located on the side of the machine.
 The extractor should be anchored in a perfectly vertical position and can be
fixed to the site structure with M8 screws (not supplied) affixed to the threaded
holes on the chassis.
19

Publicité

Table des Matières
loading

Ce manuel est également adapté pour:

Hib 1.250Hit 1.000Hib 1.000Hit 800Hib 800

Table des Matières