6. START-UP AND SHUTDOWN.
Electric arc hazard. Do not open any DC isolating switch if
the unit is under load.
Follow the steps indicated below to start the inverter:
Activate the inverter switch/isolating switch and set it to ON.
1.
Make sure that the solar field is connected. Activate the circuit
2.
breakers to enable the photovoltaic power supply.
Ensure the presence of grid voltage. Activate the circuit
3.
breakers to enable the grid supply. Without a grid, the unit will
not activate the generation mode.
OFF
OFF
The unit will start. The LCD screen will turn on. The next section
4.
describes the steps that must be followed and the operation
of the console.
Follow the steps below to stop and turn off the inverter:
Disable the grid power supply. Without a grid, the unit will stop
1.
generating.
Turn off the solar field supply. Activate the circuit breakers to cut
2.
off the photovoltaic power supply.
Deactivate the inverter's switch/isolating switch and set it in the
3.
OFF position.
70
ON
ON
OFF
The unit will stop. When the internal capacitors of the DC bus
4.
are fully discharged and have no voltage, the LCD screen will
turn off.
ON
ON