PE 2001T
2 COLUMNS ASYMETRIC POST LIFT 400V 4T
3 INSTALLATION OF THE TWO COLUMNS
WARNING:
After drilling the floor with a drill with a Ø20mm tip, anchor the columns to the floor by
fixing the anchoring bolts supplied. The depth of the hole must coincide with the length of
the used dowels.
4 INSTALLATION OF STEEL CABLES
Connect one side of the steel wire through the fixing hole to the trolley, pass the cable from
the upper end of the lift and connect it to the trolley of the other column. Then fasten it with
a nut. (see Figures 4, 5, 6, 7).
Ensure that there are no mistakes in the cables connections and that they are correctly
positioned inside the pulleys, both upper and lower one.
Picture 4 Cables installation scheme
Picture 3 (Columns installation)
Picture 5
Picture 6
Picture 7
37