Télécharger Imprimer la page

Raypak 399B Manuel D'installation Et D'utilisation page 48

Publicité

Les langues disponibles

Les langues disponibles

Weekly
For low-pressure heaters, test low-water cut-off de-
vice. (With at least one stage of the appliance on,
depress the low water cut-off test button, appliance
should shut-off and ignition fault light should come on.
Depress reset button to reset).
Monthly
1. Check flue, vent, stack, or outlet dampers.
2. Test fan air pressure. (See "Blower Adjustment" on
page 42.)
3. Test high and low gas pressure interlocks (if
equipped). (See "Safety Inspection" on page 43.)
Semi-Annually
1. Recalibrate all indicating and recording gauges.
2. Check flame failure detection system components.
(See "Pilot Turn-Down Test Procedure," page 43.)
3. Check firing rate control by checking the manifold
pressure. (See "Main Burner Adjustment" on page
42.)
4. Check piping and wiring of all interlocks and shut-
off valves.
Annually
1. Test flame failure detection system and pilot turn-
down. (See "Pilot Turn-Down Test Procedure,"
page 43.)
2. Test high limit and operating temperature. (See
"Post Start-Up Check," page 44.)
3. Check flame sensors.
4. Conduct a combustion test at full fire. Carbon diox-
ide should be 7.5 to 8.5% at full fire for natural gas,
and between 9.2 to 9.8% for propane gas (Carbon
monoxide should be < 150 ppm).
5. Check coils for 60 cycle hum or buzz. Check for
leaks at all valve fittings using a soapy water solu-
tion. Test other operating parts of all safety shut-off
and control valves and increase or decrease set-
tings (depending on the type of control) until the
safety circuit opens. Reset to original setting after
each device is tested.
48
6. Perform leakage test on gas valves. (See Fig. 37.)
7. Test air switch in accordance with manufacturer's
instructions. (Turn panel switch to the "On" posi-
tion until blower is proven, then turn the switch to
"Off".
8. Inspect and clean burners as necessary.
As Required
1. Recondition or replace low water cut-off device (if
equipped).
2. Check drip leg and gas strainers.
3. Perform flame failure detection and pilot turn-down
tests.
4. Check igniter. (Resistance reading should be 42-
70 ohms at ambient temperature.)
5. Check flame signal strength. (Flame signal should
be greater than 1 microamp).
6. Test safety/safety relief valves in accordance with
ASME Heater and Pressure Vessel Code Sections
VI and VII.

Publicité

loading

Ce manuel est également adapté pour:

499b649b749b899b989b1259b ... Afficher tout