Any compound used on the threaded joint of the 
gas piping shall be a type which resists the ac on 
of liquefied petroleum gas (propane / LPG). 
The gas supply line shall be gas  ght, sized, and so 
installed as to provide a supply of gas sufficient to 
meet the maximum demand of the heater and all 
other gas consuming appliances at the loca on 
without loss of pressure. 
INFORMATION
 
Refer to an approved pipe sizing chart if in doubt 
about the size of the gas line. 
Size the gas pipe 
The gas supply must be capable of handling the en re 
gas load at the loca on.  Gas line sizing is based on 
gas type, the pressure drop in the system, the gas 
pressure supplied, and gas line type.  For gas pipe siz‐
ing in the United States, refer to the Na onal Fuel Gas
Code, NFPA 54.  The below informa on is provided as 
an example.  The appropriate table from the applica‐
ble code must be used. 
1.  For some tables, you will need to determine the 
cubic feet per hour of gas required by dividing the 
gas input by the hea ng value of the gas 
(available from the local gas company).  The gas 
input needs to include all gas products at the lo‐
ca on and the maximum BTU usage at full load 
when all gas products are in use.  
2.  Use the table for your gas type and pipe type to 
Cubic Feet  
Gas Input of all gas products (BTU / HR)  
per Hour  = 
Hea ng Value of Gas (BTU / FT 
(CFH)  
find the pipe size required.  The pipe size must be 
able to provide the required cubic feet per hour 
of gas or the required BTU/hour. 
Example:   
The hea ng value of natural gas for your loca on is 
3
1000 BTU/FT
.  The gas input of the RL94i is 199,000 
BTU/HR.  Addi onal appliances at the loca on require 
65,000 BTU/hr.  Therefore the cubic feet per hour = 
(199,000 + 65,000) / 1000 = 264 FT
length is 10 feet then the 3/4 inch pipe size is capable 
3
of supplying 264 FT
/HR of natural gas. 
20 
3
/HR.  If the pipe 
VC Series Manual 
Pipe Sizing Table ‐ Natural Gas 
Schedule 40 Metallic Pipe 
Inlet Pressure:  less than 2 psi (55 inches W.C.) 
Pressure Drop:  0.3 inches W.C. 
Specific Gravity:  0.60 
cubic feet per hour 
Length  
3/4 
10 
273 
20 
188 
30 
151 
40 
129 
50 
114 
60 
104 
70 
95 
80 
89 
90 
83 
100 
79 
Pipe Sizing Table ‐ Propane Gas 
Schedule 40 Metallic Pipe 
Inlet Pressure:  11.0 inches W.C. 
Pressure Drop:  0.5 inches W.C. 
Specific Gravity:  1.50 
Capacity in Thousands of BTU per Hour 
Length  
1/2 
10 
291 
20 
200 
30 
160 
40 
137 
50 
122 
60 
110 
80 
101 
100 
94 
Pipe Size (inches) 
1 1/4 
1 1/2 
514 
1060 
353 
726 
284 
583 
243 
499 
215 
442 
195 
400 
179 
368 
167 
343 
157 
322 
148 
304 
Pipe Size (inches) 
3/4 
1 1/4 
608 
1150 
2350 
418 
787 
1620 
336 
632 
1300 
287 
541 
1110 
255 
480 
231 
434 
212 
400 
197 
372 
1580 
1090 
873 
747 
662 
600 
552 
514 
482 
455 
985 
892 
821 
763 