Commissioning/Decommissioning

6.1

Commissioning

NOTICE
The pump may not be turned on if there is no guarantee that the
BADU OmniTronic will take control of the pump. It must also be
ensured that the pump does not turn on when the valve is turning.
Close the transparent lid bevor the device is connected to the
power supply.
6.2

Functional test

6.2.1

Test cycle

Once the supply voltage has been applied and the BADU
OmniTronic has been turned on with the illuminated rocker switch,
the device runs a test cycle. This ends in the position "Filter".
Then the device is ready for operation.
6.2.2

Shut-off valves

The integrated shut-off valves in the BADU OmniTronic
connection lines must be opened completely.