Installation and start-up of KEOR HPE UPS 60÷80 kVA
Installation et démarrage de l'ASI KEOR HPE 60÷80 kVA
Installazione e avviamento KEOR HPE UPS 60÷80 kVA
18) Once insertion is complete of the 18 trays, carry out the last operations to terminate connection.
Battery voltage
Ensure the BCB switch is open.
19) From the right hand side of the UPS, partially extract tray no. 1 and insert the missing jumper as
indicated in the Picture 25
Picture 25 - View from above Level No.1 with battery connections
Battery voltage
ATTENTION DANGEROUS VOLTAGE
After closing the jumper, dangerous voltage will be present on the battery terminals
represented in Picture 11.
20) Repeat the operation indicated in point no. 19 for the trays
no. 4-7-10-13-16 (Pict. 9-10).