6- TEST OPERATION
1.- The test operation must be carried out after
the entire installation has been completed.
2.- Please confi rm the following points before the
test operation:
The fancoil is installed properly.
Tubing and wiring are correctly completed.
The water pipe system is leakage-checked.the
drainage is unimpeded.
The heating insulation works well.
The ground wiring is connected correctly.
The length of the tubing has been recorded.
The power voltage fi ts the rated voltage of the
air conditioner.
There is no obstacle at the outlet and inlet of
the unit.
The air conditioner is pre-heated by turning on
the power.
3.- According to the user's requirement, install
the remote controller frame where the
remote controller's signal can reach the unit
smoothly.
4.- Test operation
Set the fancoil under the mode of "COOLING"
with the remote controller, and check the
following points. If there is any malfunction,
please resolve it according to the chapter
"Troubleshooting" in the "Owner's Manual".
Whether the switch on the remote controller
works well.
Whether the buttons on the remote controller
works well.
Whether the air fl ow louver moves normally.
Whether the room temperature is adjusted
well.
Whether the indicator lights normally.
Whether the temporary buttons works well.
Whether the drainage is normal.
Whether there is vibration or abnormal noise
during operation.
Whether the air conditioner heats well in the
case of the HEATING/COOLING type.
18