8. Commissioning

Verify the following check list before commissioning the LATENTO XW. Start
running the LATENTO only when you can answer all questions with "yes".
Has the container been sufficiently filled with water?
Has the reheating heat exchanger (heating circuit) been
correctly connected?
Has the DHW heat exchanger been correctly connected
including shut-off valves and pressure-rinsing connections?
Are the heating circuits filled and bled?
Are all temperature sensors installed at the right position
and connected to the regulation unit?
Is the storage tank cover attached and closed tight?
When using the electrical heating element:
Is this element screwed tight in the cover and has been
connected by an expert?
Have all connection pipes and fittings been insulated
conforming to standards?
Are pumps and heat generator connected to the
regulation unit correctly?