OPERATION TESTING
Although quality and operation of each component are controlled by the factory at the delivery, before sale,
eventually, before the final test of the plant, an operation testing should be carried out.
TEST RUN AFTER THE ASSEMBLY
Clean the guides before the first test run takes place.
Before the beginning of the run, leave the elevator shaft free from persons and objects.
Before the general test takes place, it is necessary to slowly run through the whole area of action (with
inspection control device). After that, verify the distance to be sufficient for all fastening parts (particularly in
the fixing area of the guides and of the governor rope).
If possible before that, locate and remove screw projections and other dangerous narrow points.
Subsequently, a static function test has to be carried out:
Overspeed governor R10BF
• operate the overspeed governor by hand, pushing down the rocker lever that causes the automatic lock of
the governor and the release of the moving cheek for rope locking.
• Drive the elevator car slowly downwards.
Crush danger!
During this operation, never put the hands or other parts of the body inside the governor, because
the release of the moving cheek could cause injuries.
Overspeed governor R12BF
• Operate the overspeed governor by hand, thus causing the intervention of the moving cheek for rope locking
through the side shifting of the release lever positioned on the electric switch.
• Drive the elevator car slowly downwards.
Crush danger!
During this operation, never put the hands or other parts of the body inside the governor, because
the release of the moving cheek could cause injuries.