Télécharger Imprimer la page

Thermolec DCC-11-PCB Serie Manuel D'installation page 11

Publicité

Les langues disponibles

Les langues disponibles

STEP 7 (OPTIONAL): CONNECTION TO A THIRD PARTY
ENERGY MANAGEMENT SYSTEM
1. If a third-party system is to control the DCC, connect
the "EMS IN" input (black terminal) to the "dry contact"
output of the third-party energy management system.
2. If required, connect the output (EMS OUT) to the next
DCC to be controlled. The recommended cable for the
control signal is a twisted copper pair, 18 gauge minimum
and 14 gauge if multi-stranded.
3. For the Cristal Controls LS-100 control panel (external power
management system recommended), the configuration on the
Outputs tab of the configuration software should be as follows:
Cycling
Number of outputs used to control DCCs.
Load kW
The maximum load associated with each LS-100
output (e.g., 7.7 kW per DCC-9-40)
Min OFF (sec) 900 sec. This is the minimum amount of time a
charger must remain off.
Delay ON
300 sec. This is the time between the successive
activation of two outputs and corresponds to the
start-up time of the charger.
Delay OFF
2 sec.
Cycle delay
7200 sec (2 hours)
For questions about other LS-100 system configuration settings, see
www.cristalcontrols.com/en/support-and-resources/