APPLICATION
Electric vehicle recovery time
Following a power cut to the electric vehicle supply equipment (EVSE), a 15
minutes delay is initiated to monitor the total consumption of the electrical
system. Power to the vehicle will then be restored if the power required by
the total of the loads is less than 80% of the main circuit breaker and if
the control input for the energy management system is in the closed state
(closed contact).
Electric vehicle charging time
It is recommended to schedule the charging vehicle program during
hours of low electrical consumption to minimize interruptions to the
electric charging station.
MAINTENANCE
Do not use any cleaning solvents to clean the DCC.
LIGHTS CODE
Green
Green
Orange
Orange
Red
OFF
The charging station is energized.
The charging station is energized. The total
load exceeds 80%. If the loads exceed 80% for
a predetermined period, the charging station
will be de-energized.
The charging station is not energized. The total
loads exceed the setpoint . The resumption
time will start when the total load will allow
the charging station's load to be added without
exceeding the setpoint
The charging station is not energized. The
total load is lower than the setpoint minus the
charging station load and the recovery time is
in progress. Each flash mean two (2) minutes
before the resumption of power to the charging
station. (ex: 3 flashes = 6 minutes before power
to the charging station). During that period, if
the total load exceeds the setpoint minus the
charging station load, the recovery time will
restart from the beginning.
Malfunction:
1. Check all connections and voltage.
2. Check the DIP switch configuration settings.
3. Check if the current transformers (CT) are
properly connected and interlocked.
4. Check if the connection for the current
transformers are properly connected to the
PCB electronics.
5. If the problem persists, send pictures of the
installation at support@rve-usa.com and
then call 1 (833) 717-1355.
No power. Check the power source.