GB
PAGE 58
20: Assembly of the side wind bracing
Note: During assembly of the side wind bracing,
please make sure that you insert these wind bracing
elements as described in the relevant assembly
previews (side).
Drawing, center, left: Assembly preview - 2 panels
Drawing, center, right: Assembly preview - 3
panels
Bottom drawing: Assembly preview - 4 panels
PAGE 60
21: Assembly of the roof wind bracing
Note: During assembly of the roof wind bracing,
please make sure that you insert the wind bracing
elements as described in the relevant assembly
previews (roof). This is essential for providing the
required stability for the greenhouse.
Drawing, center, left: Assembly preview - 2 panels
Drawing, center, right: Assembly preview - 3
panels
Bottom drawing: Assembly preview - 4 panels
PAGE 62
Installation of the base assembly
Important note:
Before continuing with the installation of the PVC
panels, you will need to position your equipment
shed in its final position and attach it to its base
(concrete or brickwork base). Later on it will no
longer be possible to move the equipment shed.
Anchoring on a concrete / brickwork base.
The following additional installation materials are
required for anchoring the greenhouse on a concrete
or brickwork base (not included in the delivery
package):
Anchor fittings / dowels
Hexagon-head wood screws
Washers
You will require 1 each of these items for every floor
corner connector and 2 each for every floor gusset
plate and the mounting bracket.
Important: Use anchor fittings / dowels which are
suitable for a concrete / brickwork base.
8
Holes need to be pre-drilled in the base for the
anchor fittings / dowels.
To mark the holes, position the greenhouse on the
base and mark the positions of the holes for the
mounting brackets.
Note:
Ensure that there is sufficient space (s) between the
bore holes and the edge of the internal base.
PAGE 65
22: Installing the PVC panels and air inlets on the
front wall
Important note:
Install the PVC panels so that the recesses in the
panels face towards the external side of the
equipment shed.
Please check the exact length specifications for the
single and double clips and measure the lengths
before you install the clips.
PAGE 66
22/a: Assembly preview (external view)
Fit an h-profile to the bottom of a PVC panel 600 x
692 mm (Item 9). Tap the h-profile gently with a
rubber mallet so that it engages correctly on the
panel. Ensure that the longer side of the h-profile
points towards the inside of the panel (see profile
view).
Attach a connecting profile (Item 5) to the top end of
the panel and place a further panel on it. A triangular
shaped PVC panel is fitted to the top (Item 10 / 11).
An angled connecting profile (cut off at an angle on
the edge) (Item 6) is placed between the two panels.
Refer to the profile views during assembly.
PAGE 67
22/b: External view
Now insert the pre-fitted panels into the front wall.
Make sure that the h-profile of the panels is inserted
into the notches on the floor profile as shown in the
middle figures. The panels are fastened as shown in
Step 22/d.
Important note: Make sure that the PVC panels are
positioned on the crossmember so that they make
contact in the way shown in the Figure bottom left.