Preliminary checks and installation of the foundation plate
PRELIMINARY CHECKS BEFORE INSTALLATION
• Before proceeding with the installation, move the gate manually to check the mechanical conditions and if the movement is regular and friction-free.
• Check that the gate is structurally sound and check that the gate leaf is stable. The gate may cause injury or damage to property in the event of derailing
or falling to one side.
• The guide rail must be securely fixed to the ground and must be perfectly straight, with no kinks or other irregularities which may obstruct the movement
of the gate leaf, and must not have a gradient greater than 0.5%.
• Check that the guide rails are in good condition and adequately greased.
• Always install mechanical stops in the gate open and gate closed positions, anchored securely to the ground and with elastic damper elements (e.g. rubber
buffer) to attenuate the impact of the gate leaf against the stop.
• Check that, when the motor is unlocked, the door doesn't move if left in any position.
INSTALLING FOUNDATION PLATE
• The automation system may be installed on the right or left hand side.
• Fit the four 10MA nuts onto the anchor bolts included, tightening along the full length of the thread.
• Fit the anchor bolts into the 4 holes in the foundation plate and fasten with the 4 nuts as shown in figure 1.
• Referring to the measurements given in the figure, cast a slab of cement with the base plate sunk into the cement. The plate must be perfectly level and
clean.
• The distances between the foundation plate [B] and the rack [A] must be as indicated.
• The flexible conduits of the electrical system must exit from the hole on the right hand side of the foundation plate (seen from the inner side).
B
Fig. 1
8
Installation drive unit
• Undo the screws of the cover and remove the lid by lifting up as shown in fig. 1. Check that the six adjuster feet do not protrude from the base of the
gearmotor.
• Put the O-ring (B) onto each screws M10x40 (A). Insert the screws in the gearmotor corners (C) and secure them with the nuts M10 (D).
• Fit the BH30 on the 4 anchor bolt, as shown in fig. 2. If necessary, undo the nuts on the foundation plate.
• Adjust the horizontal position of the gearmotor by sliding along the slots on the foundation plate.
• When adjusting the vertical position, also consider the correct fastener measurements for the rack. See paragraph 9.
• Fit the spacer M10 (E).
• Fit the cover.
Fig. 1