Installation Guide
Perform network test
Once the Danfoss Link™ DBR and all other devices in the system
have been registered and the Danfoss Link™ CC is placed in
its final position, perform a network test (see
separate Danfoss Link™ CC manual).
Note: If the connection to the Danfoss Link™ CC is
lost for more than 1½ hour, the Danfoss Link™
DBR will go into safety mode. In this mode the
boiler will be turned ON continuously.
Factory reset
Turn off the power to the device, then press and hold the install
button in front of the device for approx. 5 sec. while the power
is switched on again. The button must be held until LED gives a
red flash.
Status indicator
Green LED OFF
Green LED ON
Green LED fast flash
Green LED short flash
Red LED slow flash
Danfoss Link™ DBR
Relay OFF/Standby
Relay ON/Heating
Adding or link test
Ready for adding
Adding not OK
Link test not OK
Safe State Active
VIIOS202
© Danfoss
07/2017