Commissioning, Operation - WIKA PG43SA-D Mode D'emploi

Table des Matières

Publicité

Les langues disponibles

Les langues disponibles

5. Commissioning, operation

5. Commissioning, operation
5.1 Mounting preparation
To protect the instrument from mechanical damage keep it in the
outer carton until installation.
EN
The measuring instrument should only be removed from the
packaging shortly before mounting at the measuring point.
With CIP (cleaning in place) it is recommended to clean the
measuring instrument again after mounting, using the established
process of the operator.
With COP (cleaning out of place) it is recommended to clean the
measuring instrument again before mounting, using the estab-
lished process of the operator.
On removal from the packaging, and during mounting, particular
care must be taken to avoid damage and any mechanical defor-
mation to the diaphragm.
Check the zero point. In case of a zero offset, carry out a zero
point setting. See chapter 5.7 "External zero point setting".
5.2 Installation
Do not damage the diaphragm; scratches on the diaphragm (e.g.
from sharp-edged objects) are the main causes of corrosion.
For sealing, choose appropriate seals.
For flange mounting, only use sealings with a sufficiently large
inner diameter and centre them; contact with the diaphragm leads
to measuring errors.
When using soft or PTFE sealings, observe the instructions of the
sealing manufacturer, particularly with regard to tightening torque
and load cycles.
12
WIKA operating instructions disphragm pressure gauge, model PG43SA-D

Publicité

Table des Matières
loading

Table des Matières