10. Welding the guide profile in place for the drawbridge leveller, type Z
10.1
EN
10.2
Preparation
•
First of all, check that the position where the drawbridge leveller is to be installed offers adequate free space for operation when in use.
•
Make sure that the guide profile is completely straight before tack-welding it in place. When tack-welding the profile in place, make
sure that the vertical axis of the guide profile is perfectly vertical.
•
Packing is required if there is a gap of more than 1 mm between the guide profile (1) and the steel U profile (2).
•
Before welding, the zinc coating should be removed in the area of the welded joint.
•
The guide profile must be attached in the horizontal position to the steel U profile with individual tack welds.
Important!
The guide profile must be perfectly level and perpendicular!
•
The guide profile (1) must then be welded along its entire length to the steel U profile (2), starting from the middle and in accordance
with the figure.
•
All of the slotted holes must be welded as shown.
12
This installation manual must be given to the customer and kept safely during the entire period of use!
1 Guide profile
2 Steel U profile (third-party supply)
3 End stop (not in scope of supply, responsibility of installer)
All dimensions in mm
General instruction: The image may differ at detail level.