All large stones must be removed, after the excavation of the trench. Punctual loads (corners or
sharp stones) can cause damage.
As base plate, an about 15cm thick concrete plate needs to be brought into.
Now, with the support of ropes (wooden beams inside the
underground tank) crane, the GEOtank will be dropped into the
trench (Illustration 3).
Please note that the subsidence does not take place one sided,
but
over the hole area parallel to the sandbed. Set up the
container with a bar and a spirit level afterwards.
service cover
Servicedeckel
Ausrichtung des Tanks
ß nach DIN 4124
O
330 cm
Base plate
Grundplatte 15cm
Montagedeckel
heating
Heizkessel
Illustration 2: trench
50 cm
Servicedeckel
Open service cover
öffnen
The GEOtank must be set up in a way, that the service lid
will show in the opposite direction of the heating
installation, otherwise problems by laying the hose can
occur. (see illustration 4)
V00070130
At any coverage of the tank of
more than 50 cm, a conductance of
weight made of concrete (s= ca 10
cm), must be made over the entire
excavation.