8 Putting out of operation

NOTE
• When decommissioning the system, ensure that the procedures for switching off the weld-
ing components are observed.
• As liquid-cooled cable assemblies start to leak when they overheat, the cooling unit
should continue running for approx. 5 min. after welding.
1 Wait until the shielding gas flow has subsided.
2 Close the shut-off valve for the gas supply.
3 Switch off the power supply.

9 Maintenance and cleaning

Scheduled maintenance and cleaning is a prerequisite for a long life and a trouble-free
operation.
DANGER
Risk of injury due to unexpected start
The following instructions must be adhered to during all maintenance, servicing, assembly,
disassembly and repair work:
• Switch off the power source.
• Close the gas supply.
• Close off the coolant supply.
• Disconnect the coolant supply and return hoses.
• Disconnect all electrical connections.
• Switch off the entire welding system.
DANGER
Electric shock
Dangerous voltage due to defective cables.
• Check all live cables and connections for proper installation and damage.
• Replace any damaged, deformed or worn parts.
DANGER
Risk of burns
Risk of burns from hot coolant and hot surfaces.
• Switch off the coolant recirculator before starting maintenance, servicing, assembly,
disassembly and repair work.
• Allow the welding torches to cool down.
• Wear the correct protective gloves.