1
TX20
Tightening torque 1,5 Nm
3.
Open the installation box hatch by removing the fastening screws (2 pcs) / unlocking the hatch lock [1].
4.
Remove the entire installation box cover by unscrewing the fastening screws (4 pcs) [2].
5.
Hang the charging station on the screw you attached to the wall.
6.
Attach the charging station on wall with two washers and fastening screws (not included) [3].
Be careful not to damage the fixed charging cable!
7.
Pull the electrical cables approx. 150mm through the cable glands.
8.
Cut the supply cable conductors in suitable lengths. Leave the ground conductor long enough so that if
a fault occurs it is the last one that comes loose.
9.
Strip the conductors 11 mm and connect to the supply connectors.
10. Load management connections: If it is necessary to connect the charging station to an energy meter or
an external control device, connect the required control cable to the pre-installed connector [4].
11. Put the installation box cover back in right position and fasten with the screws you removed.
12. Close the installation box hatch.