Télécharger Imprimer la page

Rheem GEN42WN Manuel D'installation Et Démarrage page 16

Publicité

Battery
The residential generator is supplied with a valve-regulated
rechargeable 12 Volt battery. The battery cables are
connected at the factory. The unit's 15 Amp fuse has been
removed from the control panel to prevent the unit from
starting in transit.
WaRNING
Battery posts, terminals and related
accessories contain lead and lead compounds,
chemicals known to the State of California to
cause cancer and reproductive harm. Wash
hands after handling.
The battery may not be at full charge when installed. If
battery voltage is below 12 Volts, charge the battery.
See Battery in Maintenance of the operator's manual
for details.
Fuel Supply System
Ensure that all fuel pipe connections are tight, secure and
without leaks.
Ensure that all gas line shutoff valves are OPEN and that
adequate fuel pressure is available whenever automatic
operation is desired.
Initial Start-up (No Load)
Before operating the residential generator or placing it into
service, inspect the entire installation carefully. Then begin
testing the system without any electrical loads connected,
as follows:
NOTE: Unit has been set-up for NG or LP vapor operation
at the factory. Fuel conversion, if needed, must be completed
prior to performing these steps.
1. Set generator's main circuit breaker to its ON
(closed) position.
2. Confirm 15 Amp fuse is installed in system
control panel.
3. Set generator's system switch to AUTO.
4. Push and hold MANUAL OVER‑RIDE button on
control panel for about six seconds. Engine will start.
NOTE: When the generator is started for the very first time,
it will require that air in the gaseous fuel lines be purged.
This may take a few minutes.
16
5. Listen for unusual noises, vibration or other indications
of abnormal operation. Check for oil or coolant leaks
while engine runs.
6. Let engine warm up for about five minutes to allow
internal temperatures to stabilize.
7. Connect an accurate AC voltmeter and a frequency
meter to check generator output at load side of circuit
breaker. No-load voltage should be 239 - 244 Volts,
frequency should be 59.8 - 60.2 Hz.
NOTE: If AC voltage is outside these ranges, perform the
generator adjustment, Steps 10 and 11 below.
8. Check generator output between one of the generator
connection lugs and the neutral lug, then between the
other generator connection lug and the neutral lug. In
both cases, voltage reading should be 117 - 123 Volts.
IMPORTANT: DO NOT proceed until you are certain that
generator AC voltage is correct and within the stated limits.
Generator frequency is fixed and not adjustable.
9. If voltage and frequency values are correct, proceed to
step 12.
10. Connect voltmeter as described in step 7 above.
11. While observing voltmeter, adjust alternator voltage
control (A) for 240 volts. DO NOT adjust either of the
other alternator controls.
a
12. Push and hold MANUAL OVER-RIDE button on control
panel until engine stops.
13. Install alternator circuit breaker enclosure cover.

Publicité