8. Installation / Commissioning checklist
Introduction
Examine the mechanical and electrical installation in accordance with this checklist to make sure that the
charging station is properly installed.
Checking the Installation
Examine the visual, mechanical and electrical installation when the charging station is un-pow-
ered.
CATEGORY
Overall look
Mechanical
installation
Electrical
installation
Operational
check
Ready for use
42 / 68
X
ITEM
You have received the ordered material.
You do not see any scratches or damages.
The charging station is fixed properly on the installation site.
Charging station's power supply capacity meets the electrical planning (cable
size, protective devices...).
Review the local electrical design plan.
The PE-cable screw is tight.
The power supply conductors (L1, L2, L3, N and PE) are properly connected.
The insulation of the power supply cable and conductors (L1, L2, L3, N and PE)
is intact.
TN / TT
network:
•
The voltage between PE and N is less than 10 V.
IT network:
•
The voltage between L1 and N is 230 V.
•
The voltage between L1 and PE is 130 V.
The PE conductor resistance is less than 3 Ω.
The load management control cables meet the electrical planning requirements,
if in use.
All the LED states / color (green, blue, red) are functioning.
•
Use a car simulator.
•
Create fail and charge.
•
Red at bootup, green at idle and blue while charging.
Test the functionality of load management, if in use.
Test the functionality of the protective device.
Correct software is in use.
LERAK131B_20221004