EN-6
3. Basic requirements and installation
3.1. Basic requirements
Ensure that the installation is performed according to the instructions, and the
surface is flat in the area where the scale will be positioned,
The Height difference of the surface must not exceed 1mm. The maximum
weight capacity of the surface at the four cell feet position should be higher
than the maximum allowed weight of the cell.
3.2. Standard installation
1.
Unpack the wooden box and take out the product. Remove all packages.
2.
Choose an installation location. Place the weighing platform on the
ground and connect it with the ramp. Whole scale positioning (as shown
below).
b
a
LEGEND: a. Ramp, b. Footplate, c. Expansion bolts hole, d. Expansion bolts,
e. Lock handle, f. Safety buckle
Figure 3-1 Ramp Installation
Defender Series Floor Scale
f
e
c
d