5. Installation Check-up

WARNING: AFTER INSTALLATION, CHECK TO SEE IF THE MACHINE IS WORKING PROPERLY (see the
Installation Module C)
WATER CONNECTIONS
No leaks from the connections or tubes
FUNCTIONING
Boiler and operating pressures are normal.
The pressure gauge is working properly.
The self-levelling device is working properly.
The expansion valves are working properly
WARNING: ONCE THE MACHINE HAS BEEN INSTALLED AND IS READY FOR USE, BEFORE ALLOWING
THE WORKER TO START USING THE MACHINE, WASH THE INTERNAL COMPONENTS ACCORDING
TO THE INSTRUCTIONS BELOW:
GROUPS
Hook up the lter holders to the groups (without coffee).
Let each group dispense water for about a minute.

HOT WATER

GT - HD: continuously dispense hot water (pressing the appropriate button) until at least 5 litres of water have been
used.
DT: continuously dispense hot water (pressing the appropriate button) until at least 5 litres of water have been
dispensed for a machine with 2 groups, 8 litres for a machine with 3 groups and 10 litres for a machine with 4 groups.
See the "Hot water dispensing" chapter in the User's Manual.
STEAM (also with Turbosteam)
Dispense steam from the nozzles for about a minute, using the appropriate buttons.
TURBO MILK (where applicable)
After removing the intake tube from the milk container, carry out a few test cycles.
.
6 EN