11 Commissioning

MPS
stations are generally shipped:
Fully assembled
Individually adjusted and ready for use
Pre-commissioned
Tested
Note
When stations are combined, the mechanical setup as well as sensor positions and settings may
have to be changed.
Commissioning is normally limited to visual inspection in order to ensure correct tubing connections, wiring
and operating voltage supply.
All components, tubing connections and cabling are clearly identified so that all of the connections can be
readily restored as required.

11.1 Workstation

You'll need the following in order to commission the MPS
The assembled and adjusted MPS
A control console
A PLC board with 16 digital inputs and outputs
A power supply unit: 24 V DC, 4 A ≤ 100 W
Compressed air supply: 600 kPa (6 bar)
A PC with installed PLC programming software
Two I/O cables (SysLink)
© Festo Didactic 8103339