Commissioning

8.1 General Information

To ensure proper commissioning it should be carried out by a
customer service authorised by the manufacturer. This will lead,
under certain circumstances, to an extension of the warranty pe-
riod (cf. Warranty). Start-up should be carried out in heating op-
eration.

8.2 Preparatory Steps

Prior to commissioning, the following items need to be checked:
All connections of the heat pump must have been made as
described in Chapter 7.
The heat source system and the heating circuit must have
been filled and checked.
The strainer must have been fitted in the sole inlet of the
heat pump.
In the brine and heating circuits all valves that might impair
the proper flow must be open.
The settings of the heat pump controller must be adapted to
the heating installation in accordance with the instructions
contained in the controller's operating manual.

8.3 Commissioning Procedure

The start-up of the heat pump is effected via the heat pump con-
troller.
ATTENTION!
Commissioning is to be effected in accordance with the installation and
operating manual of the heat pump controller.
Any malfunctions occurring during operation are displayed on the
heat pump controller and can be corrected as described in the
operating manual of the heat pump controller.