√ Check whether the earth connection is mounted on the connection terminal in
accordance with the NEN1010/EU/35 standard.
√ Check whether the cable thickness of the power cable matches the fused
current rating.
√ Check whether the charging station is tightly and properly secured.
√ Check whether the station is sufficiently waterproof.
√ Keep the immediate environment of the work area free from obstacles.
Before the power is connected to the charging station, you must first call Ecotap® B.V.
on +31 (0)411 745 020 (Mo – Fr 09:00 to 16:00) so that we can activate its software (this
requires the unique charging station number).
19. OPERATING / INSTALLATION MANUAL
19.1 Open the door
The door can be opened in the following way.
Insert the key supplied and turn it until the handle unlocks.
Turn the handle so the door will unlock.
Carry out these steps in reverse to close and lock the door.
19.2 Mounting on the foundation
To fit the foundation, a hole must be dug of roughly L 750 mm x D 450 mm x H 530 mm.
The bottom of the hole must be stable and levelled.
Place the foundation base level in the hole. The upper surface of the base must be flush with
the upper surface of the grade / paving. The foundation must then be reinforced by adding
at least two 20 kg bags of fast-setting concrete in the corners of the foundation.
After the fast-setting concrete has cured, the charging station can be mounted on its
foundation using the nuts and bolts provided (nuts to the top).
The hole in the foundation and the charging station must be lined up. See drawing of the
topview of the foundation base. Take account of the connection face of the charging station
in relation to walls, hedges, etc.
Always ensure that the doors are fully open!
Also keep in mind that there is sufficient space for the operation of the charging station. For
this we advise to keep at least 1 meter of free space around the charging station.
20. www.ecotap.nl
20/04/22