5.2.2
30233018C Quick Pit for PFK9-series, sizes D/E/ES
Variant 2 – Placing the frame into the rough pit
2
1. Screw the 4 threaded rods (1) through the frame until they contact the bottom of the
rough pit.
2. Level the frame exactly and secure with the nuts (2).
Note
Only an exactly levelled frame guarantees the best weighing results.

5.3 Concreting

1. Encase the frame in concrete. Use the concrete quality in accordance with the
specification by the architect or structural engineer.
2. Let the concrete harden in accordance with the specifications of the concrete
manufacturer.

5.4 Completion

After the concrete has hardened:
1. Screw the nuts from the threaded rods.
2. Variant 1: Turn out the threaded rod and remove with the support beams.
Variant 2: Saw/cut off the protruding threaded rods.
3. In the case of moist environments seal the masonry with suitable material.